Agogo
Offshore CCS
Carbon Circle is executing the Engineering, Procurement & Construction contract awarded by Yinson Production for a Post Combustion Carbon Capture and Storage unit.
The PCCCS unit will be installed on Yinson’s FPSO for the Agogo Integrated West Hub Development Project in Angola and it is the world's first PCCCS on a offshore production unit.

Scope
EPC of world's-first post-combustion CO2 capture plant
Industry
Oil&Gas
Location
Offshore Angola
Capacity
2000 tonnes CO2/year
Seal Sands
EfWICC
Carbon Circle has completed the FEED engineering contract for design of the Seal Sands Energy-from-Waste Plant with Integrated Carbon Capture (EfWICC), producing green, renewable energy based on reception, handling, and gasification of waste.
The plant consists of 4 Advanced Conversion Technology gasification lines, with an annual combined capacity of 200,000 tonnes waste, with a 290,000 tonnes CO2 capture capacity.

Scope
FEED for a complete Energy-from-Waste facility with Integrated Carbon Capture and Intermediate CO2 Storage
Industry
Energy-from-Waste
Location
Middlesbrough, UK
Client
Solar21
Capacity
200.000 ton waste/year
290.000 ton CO2/year
Aintree
Offshore CCS
Carbon Circle has conducted a Pre-FEED study on design of a complete FPSO Process- & Utility Topside, including facilities for full-scale post combustion carbon capture, CO2 conditioning and reinjection.
This innovative project involves revitalization of an undisclosed UK O&G field and includes conversion of a last-generation drill-ship candidate, with a robust hull design. Captured CO2 is to be conditioned and reinjected into nearby geologies for permanent sequestration.
Should the project materialize, it will be the world’s first full-scale post combustion CCS system ever implemented on an FPSO. The topside is spread over 9 modules with a combined weight of around 6,000Te.

Scope
Pre-FEED for full-scale offshore CCS facility
Industry
Oil&Gas
Location
Undisclosed
Capacity
70.000 ton ton CO2/year
Stella Maris
Fixed Injection Unit
Carbon Circle has been engaged by Stella Maris CCS to perform a concept screening study for a Fixed CO2 Injection Unit (FIU) to the Havstjerne CO2 Injection Licence.
The scope of the study included demonstrate technical feasibility of deploying the Havstjerne Project by applying an unmanned jacket platform and to establish CAPEX Estimates and Level 1 Schedules.

Scope
Feasibility Study for an unmanned CO2 Fixed Injection Unit
Industry
CO2 Storage
Location
North Sea, Norway
Client
Stella Maris CCS AS
Capacity
1.5 Mtpa CO2 injection (initial)